You are on PERI's international website. Click here to switch to PERI USA. Click here to view all PERI websites.
Construction of the 210 m long section between the seventh and tenth bridge piers in 48 casting segments using the balanced cantilever method.
Contractor
Dragados S.A.
Field Service
PERI Poland Sp. z o.o., Krakau and Warsaw Branch Offices, PERI GmbH Weissenhorn
The PERI cantilevered construction solution provided us with many advantages: fast realization due to the well thought-out and easy handling as well as compliance with the required tolerances thanks to the practical formwork adjustment which allowed very accurate construction of the webs. In addition, the compatibility with PERI UP facilitated safe access means and working areas without any extra time and effort - indispensable for the execution of such a project.